Accelerating disbursement of public investment projects, Vice Chairman of the PPC urged

ABO - On May 15, the Tien Giang provincial People's Committee (PPC) held a conference to review and evaluate the implementation of public investment plans in 2019.

At the conference. Photo: M.THANH
At the conference.

According to the Tien Giang province Department of Planning and Investment, the total public investment capital from the state budget in 2019 was 3,846.3 billion VND.

Basing on the allocated capital, the province has implemented 462 works and projects (in which, the provincial level manages 147 works and projects; the district level manages 315 works and projects).

By the end of day 2-5, the total value of disbursed public investment capital in the province was 715.7 billion VND, reaching 18.7% of the plan, etc...

The disbursement rate of works was slow due to many reasons: The branches and localities focused on checking and settling the capital plan in 2018 until the end of January, 2019; focusing on completing the investment procedures and selecting contractors for new construction projects.

Chairman of Go Cong Tay District People's Committee Dinh Tan Hoang reported the progress of public investment in the locality.
Chairman of Go Cong Tay district People's Committee Dinh Tan Hoang reports the progress of public investment in the locality. Photo: M.THANH

In addition, compensation and site clearance still faces many households, which slow down the progress of implementing a number of important projects such as provincial road 877B (the section passing through Tan Phu Dong district center) and district roads. 60, provincial road 878 ...

At the conference, leaders of departments, agencies and localities reported on the progress of public investment projects and projects invested by the units; at the same time, raising difficulties and obstacles in the implementation process.

Speaking at the conference, Vice Chairman of the PPC Pham Anh Tuan asked localities to speed up the construction progress of transition works from 2018 to; completing bidding procedures for new projects.
From now until the end of June, the disbursement rate must reach over 50%, especially the central capital sources allocated to achieve the set objectives and plans, etc...

By M. THANH – Translated by HUU TAM
 

.
.
.