The Standing Committee of the Tien Giang provincial Party Committee surveys Trung Luong-My Thuan expressway

ABO - On May 27, the delegation of the Standing Committee of the Tien Giang provincial Party Committee and leaders of departments, branches with Trung Luong - My Thuan BOT joint stock company (as the project enterprise) had a field work at Trung Luong - My Thuan expressway project.

danh
Leaders of the province survey the actual project at Than Cuu Nghia intersection.

Accordingly, the delegation surveyed some positions of the project to find out the reality at the construction site; at the same time, listening to the project enterprise to report the progress of construction of the bidding packages, difficulties in the implementation process, etc...

According to the Tien Giang provincial People's Committee, the project has a length of 51.1 km and a total investment of 9,669 billion VND under the Decision 1700/QD-BGTVT dated June 15, 2017 of the Ministry of Transport and Transport.

danh
Secretary of the Tien Giang provincial Party Committee Nguyen Van Danh (left cover) with the comrades of the Standing Committee of the Provincial Party Committee survey the actual project. Photo: M.THANH

The total investment in the clearance project is 1,689 billion VND. Up to now, 411/3,292 households have not received compensation money.

Currently, the province has handed over clean ground on the main route of the project, reaching 99.09%. Regarding the progress of implementing the bidding packages, the project enterprise has so far implemented 19 construction and installation packages, the construction volume of the whole project is about 17.84%.

Regarding the responsibility of the Tien Giang province for the project, the Provincial People's Committee periodically meets with the steering committee of the Trung Luong - My Thuan expressway construction project phase 1 under the form of BOT and professional teams of the steering committee to check the implementation of the project, removing difficulties and obstacles and directing some contents to focus on the next implementation, etc...

By M.THANH – Translated by HUU CHI

.
.
.