ABO - On August 14, Chairman of the Tien Giang provincial People's Committee (PPC) Le Van Huong and other departments and branches worked with Cai Be district on site clearance of the Trung Luong-My Thuan expressway project.

Chairman of the PPC Le Van Huong speaks at the working session.
Chairman of the PPC Le Van Huong speaks at the working session.

Up to now, in Cai Be district, there are more than 10 households who did not receive compensation and support for site clearance. Local authorities are mobilizing and solving problems so that these households can receive compensation and support. With the drastic direction of provincial leaders, Cai Be district has made great efforts in the site clearance work to hand over to investors over the past time.

At the working session, leader of Cai Be district reported difficulties and problems for each case who did not receive compensation and support for site clearance; related departments and agencies gave opinions and solutions to speed up the work of site clearance.

At the working session.
At the working session.

Speaking at the working session, Chairman of the PPC Le Van Huong praised Cai Be district for efforts in the site clearance. At the same time, he directed the settlement of each case who did not receive compensation and site clearance. He asked Cai Be district to speed up the progress of site clearance for the project, etc… Tien Giang province determined to complete the site clearance of the project by the end of August.