ABO - Speaking at the inspection of the relocation of infrastructure to implement the Trung Luong - My Thuan Expressway Project, phase 1, on the afternoon of September 20, Chairman of the PPC Le Van Huong urged, to focus on solving problems in ground clearance work.

H
Chairman of the PPC Le Van Huong speaks at the meeting.

Regarding the general affairs, Chairman of the PPC Le Van Huong assigned the Management Board of transport construction investment project to prepare a meeting for the PPC to solve problems related to the electricity relocation.

Regarding relocation of the daily-life water supply system, the districts and towns, where have  the project passes, must work frankly in the case of still having problems to ensure that the people have daily-life water, etc…

According to the Management Board of transport construction investment project, after the PPC held a physical inspection of the relocation of the project infrastructure, the unit coordinated with the districts and towns to review, checking the compensation, handing over the ground. At the same time, coordinating with Tien Giang Electricity, Tien Giang Water Supply Company Limited, Tien Giang Telecommunications, Viettel Tien Giang and electricity and telecommunication to relocate construction units.

On September 20, for handing over the site, the Cai Be Trading - Service Joint Stock Company received compensation money. , support the land and agree to hand over the construction site.

In addition, at An Thai Trung intersection, Cai Be district, the locality handed over the site on September 10. There are 9 houses which are still being dismantled.