Construction of My Thuan 2 bridge to begin by December 2019
ABO – On November 7, Vice Chairman of Tien Giang provincial People's Committee Pham Anh Tuan inspected the preparation of the groundbreaking ceremony of My Thuan 2 bridge at the connection point between Trung Luong-My Thuan Expressway Project and My Thuan 2 bridge project in An Thai Trung commune, Cai Be district.
Vice Chairman of Tien Giang provincial People's Committee Pham Anh Tuan inspected the project at the XL08 parckage. |
Regarding the work of clearance of My Thuan 2 bridge project in Tien Giang province, the locality has applied compensation prices and let people know.
It is expected that at the beginning of December, compensation and site clearance will be paid, especially for the section running through An Huu commune will be paid by the end of November.
It is expected that My Thuan 2 bridge will be started by December 2019.
Comrade Pham Anh Tuan asked the contractor of the An Thai Trung intersection to urgently level the ground to create a level at this intersection to prepare for the commencement ceremony of My Thuan 2 bridge.
At the same time, it is required that relevant units carry out the relocation of the remaining electric poles within the clearance boundaries.
In the afternoon of the same day, comrade Pham Anh Tuan also came to survey the project in the XL05 package of Cai Lay bridge construction. Particularly for the XL08 package, this package is currently behind schedule due to lack of capital.
According to the project enterprise, when the state budget support is disbursed and the contractor still construction slowly, the unit will handle.
At the survey trip, comrade Pham Anh Tuan said that the current difficulty is a common difficulty so the project enterprises and localities and related units should work together to bring the project to the right destination degree.
By M. THANH – Translated by HUU CHI