Chairman of the PPC Le Van Huong checked the new rural areas building

ABO - On October 4, Chairman of the Tien Giang provincial People's Committee (PPC) Le Van Huong and leaders of departments and branches checked the new rural areas building in Tan Phong commune of Cai Lay district and Phu Phong commune of Chau Thanh district.

* In Tan Phong commune, eight criteria are being appraised by the province and one criterion is waiting for verification.

h
Comrade Le Van Huong speaks at the working session with Tan Phong commune.

It is expected that Tan Phong commune will launch the new rural areas in late November or mid-December. In addition, leader of the commune also proposed that the provincial leadership will remove difficulties in capital construction, especially the construction of Tan Phong 2 primary school, etc…

Comrade Le Van Huong highly appreciated the efforts of Tan Phong Party Committee, authorities and people in the movement to build the new rural areas.

He also checkd the construction of Tan Phong 2 Primary school, meeting the construction unit and requiring them to speed up and ensure the quality so that Tan Phong commune could timely launch the new rural areas in 2019.

* In Phu Phong commune, comrade Le Van Huong inspected the construction of Phu Phong Secondary school. This school has a total investment of over 22.5 billion VND. Currently, the construction volume is about 28% of the value of the project with the construction contract until June 2020.

h
Comrade Le Van Huong and leaders of departments, branches check the construction of Phu Phong Secondary School.

After working with the investor and the construction unit, comrade Le Van Huong required the investor to learn experience in bidding because the time was too long, requiring the construction unit to complete the project before December 30, 2019, ensuring the quality for Phu Phong commune to launch new rural areas in 2019.

By SN – Translated by HUU CHI
 

.
.
.