My Tho commercial - service zone will operate on the occasion of September 2
ABO - The above information was given by the construction unit of My Tho commercial - service zone at the meeting with leaders of the Tien Giang provincial People's Committee (PPC) on the morning of July 9.
Leaders of the PPC check the construction progress of Tien river embankment project - Ward 2. Photo: M.THANH |
Previously, the Chairman of the PPC Le Van Huong and Deputy Chairman of the PPC Tran Thanh Duc inspected the implementation of the project Tien river embankment - ward 2 (My Tho city); the My Tho commercial - service zone; surveying on tourism exploitation of Ba Ngot canal in My Phong commune and Dao Thanh commune of My Tho city.
The Tien River embankment project has achieved 71% volume, 29% slower than the plan. For My Tho commercial-service zone, the project is in the stage of completion and installation of equipment. As expected, the project can come into operation on the occasion of September 2.
Particularly, for the survey on tourism exploitation of Ba Ngot canal, the Department of Culture, Sports and Tourism has planned to exploit to create more new tourist routes for the province.
Through the survey, for the Tien river embankment project in ward 2, Chairman of the PPC Le Van Huong asked the Urban Upgrading Project Board to invite new contractor to complete the remaining works, to give the completion of the progress.
For the My Tho commercial - service zone, the contractor should pay attention to the road to ensure traffic safety; at the same time, to repair the sidewalks on Le Van Pham street. Particularly, for the tourism exploitation of Ba Ngot canal, the Department of Culture, Sports and Tourism continued to survey to put into effective exploitation, etc...
By M.THANH – Translated by H.CHI