Chairman of the PPC Le Van Huong checks the basic construction works
ABO - On November 26, Chairman of the Tien Giang provincial People's Committee (PPC) Le Van Huong checked the progress of My Loi bridge construction project (Go Cong town) and the provincial road 872B project of Go Cong Tay district (the section from the National Highway 50 to the provincial road 877).
Comrade Le Van Huong inspects the landmark of My Loi bridge. |
My Loi bridge, located on the provincial road 873 (in the direction from My Loi to Go Cong town), has the length of the route as 1,126.66 meters with the total construction investment as about 160 billion VND. There are 60 households affected and 15 households cleared by the project. Currently, the project has finished setting up landmarks.
Chairman of the PPC Le Van Huong requested the locality to inform the people about the project. This is a state project so people will proceed with coercion if they do not clear up and receive compensation. He requested the specialized industry to select capable contractors to accelerate the implementation.
Along with Ngu Hiep bridge on the provincial road 868 in Cai Lay district and Tra Lot bridge in Cai Be district, My Loi bridge is one of the works to welcome the 11th Tien Giang provincial Party Congress (2020 - 2025).
* On the same day, comrade Le Van Huong inspected the provincial road 872B project in Go Cong Tay district (the section from the National Highway 50 to the provincial road 877).
Comrade Le Van Huong requests professional and local industries to speed up the ground clearance. |
At the inspection, comrade Le Van Huong requested the specialized industry and the People's Committee of Go Cong Tay district to accelerate the site clearance and compensation for the people, especially the first part of the National Highway 50 for construction units to accelerate the work progress.
By S.N – Translated by HUU CHI